Question 1
Before replacing a component, a qualified electrician isolates and locks out all identified supplies and controls stored energy. The site requires a voltage tester to be proved immediately before and after absence-of-voltage testing. The tester passes the initial proving check and indicates zero at every required work-point test, but fails the final check on a proving source independently confirmed to be working. No servicing has begun. What must happen before the equipment is treated as de-energized?
Show answer & explanation
Correct answer: C - Maintain isolation and repeat verification with a tester proved working before and after the tests.